In my work routine, i visit the work site of RFC and observe the progress of the work at car park level 2. So far, the form work progress is around 75 %. Form work is process of laying down the conventional wood board according to the architectural drawing before proceed with casting of the whole level 2 car park.From my observation, the form work usually takes around one week to complete.
I also visit on the infrastructure work going on at the back portion of the RFC building. The workers were laying down the ready-cast drainage block which they prefer to call it as box culvert to form the drainage system around the building. I gained some exposure from the site supervisor on how to calculate the gradient for the drainage block which is to be placed on the ground.