A short morning briefing was conducted by Mr. Yap, the senior project manager of Oasis, Ara Damansara. Shortly after the briefing, i was informed by Mr. Sarjit Singh, the administrative officer, that i will be transferred to another Brunsfield project in Kajang town. As been told, i will be reporting to Mr. Chee, the site manager on Monday, 19 April 2010. I will inform the further details about this project once i report for work on Monday.
During this last day at Oasis , i learned about the defect works on the structure column. Whenever there is a defect on the casting work on any structure particularly column beam, i was told that the pressure grout method is used to fix the defect problem. This process uses Sika Grout as the main filler material to fill up the cavity of the desired column size and shape. I will attach the photos of the process in the next post. I was told that Sika Grout have the same strength and high bonding characteristic compared to concrete cement.