Thursday, April 22, 2010
22 April 2010
Wednesday, April 21, 2010
21 April 2010 @ RFC
Tuesday, April 20, 2010
20 April 2010 @ RFC
Monday, April 19, 2010
19 April 2010 @ Regional Finance Center, Kajang
Sunday, April 18, 2010
17 April 2010 @ Oasis
16 April 2010
Thursday, April 15, 2010
15 April 2010 @ Oasis
It's Thursday and the weather is hot and sunny today. As usual, housekeeping was carried out in the morning and the targeted area was catchment platform on level 1 and 2 of block H. The task was mainly clearing up the casting waste fell from floors above. Then inspection was performed for each floor and recorded inside the site diary.
Brick laying works started on level 2 and 3. Air conditioning ducting pipes was prepared by one of the subcontractors and the installation works has started for level 2 and 3. I also manage to snap photos on each floor to show the progress on Block H. Later I was assigned task to revise and remark the dimension for openings from level 2 until level 8. Opening is the hole made to install sanitary pipes, wiring, chillers pipes and water supply pipes that works to supply and distribution around the office tower building.